18 Avenue De Triomphe

Construction Updates

Ongoing Works

Progress Update
77%
Excavation Works
  • Completed.
Civil/Structural/Architectural Works
  • Installation of wood doors at 29/F-42/F
    residential units
  • Tile works at 20/F-36/F residential units
Mechanical Works
  •  Installation of FCU at 17/F-19/F, 23/F and
    25/F
  • Installation of panel box at 38/F and
    45/F residential units
Sanitary/Plumbing/Fire-Protection Works
  • Installation of plumbing fixtures at
    14/F-15/F
  • Installation of sprinkler droppings at
    28/F-29/F

 

As of December 2024